Gliding into a better future with an $81,000 refund.

Value Brought to Project

COST

$4.9mm

AREA

38,000 sf

COMPLETION TIME

13 months

GMP SAVINGS

$81,000

ENGINEERING COST CONTAINMENT

3%

LOCATION

Middletown, RI

Challenge

A historical institution, St. George’s believes athletics acts as an extension of the classroom by reinforcing good sportsmanship, teamwork, self-discipline and responsibility. They desired a 40,000 SF addition to keep their ice hockey curriculum in top form amidst other competitive New England private schools.

Design Build Value

This extensive project consisted of two phases. First, the preexisting 1960’s ice area required structural upgrades entailing replacement of the ice sheet and roof with the addition of a newly equipped machine room. The second phase entailed a pre-engineered metal building to accommodate a second new ice arena, with support facilities, ice package and stadium seating for 160. Phased to accommodate the scholastic season, the client received $81,000 back in GMP savings.

Sports
Sports
Sports
Sports
St. George’s School
Sports

Share:

...

Related projects

Sports

Wellesley Sports Center

View More
Sports

Dexter Southfield School

View More